Oyak Aslan Cement Transfer Tower Panel Transport Electrical Works

25-09-2025

As SPD Engineering, we are pleased to announce that we have commenced the Transfer Tower Panel Relocation Electrical Works at the Oyak Aslan Cement Darıca Plant as part of our existing Electrical Works Contract, during the facility’s planned shutdown period. The scope of work includes the following activities: Identification and assessment of existing field equipment, Replacement of all electrical cables, Relocation of MCC, PLC, and drive panels, Execution of new cable laying and connection works, Preparation of as-built (post-implementation) documentation. All these processes are being carried out by our expert team in full coordination with our client. At SPD Engineering, we take great pride in contributing to this project and sharing our technical expertise with our client. We are committed to completing the project with precision, safety, and to the highest quality standards.